Short facts
Country
Germany
Service area
Overhead line construction
Project details
Customer:
50Hertz
Project start:
01.09.2022
Project duration:
09.2022 – 03.2024
Total length:
23.3 km
Foundations:
56 slabs with approx. 7,756 m³ of concrete and 18 deep foundations with bored piles
Total weight of masts:
2,484 tonnes
Cabling:
2 x 3 x 4 264-AL1/34-ST1A with 2 systems, bundle of 4
The project includes the construction of the foundation and mast assembly, pulling the cables, and erecting provisional structures.

Specific challenges:
- 110 kV provisional structure for installation of mast 124
- Crossing protection for the electrified railway line
This ambitious measure will contribute to optimising and expanding the infrastructure in the area of high-voltage lines. Efficient implementation of all safety and environmental requirements ensures that this project is completed successfully and sustainably.